16th June 2008 Work started on the main building today. |
16th June 2008 Bisley's groundworks sub-contractor S R Newman are stripping the topsoil from the footprint of the building. |
16th June 2008 The brand new excavator made short work of this task! |
17th June 2008 The area of the building has been reduced to formation level and a layer of sub-base placed and compacted. The finished building will be nearly twice this size. |
18th June 2008 Trenches for the footings have been excavated along three sides of the building. |
19th June 2008 A large heap of earth is appearing next to the building work. |
19th June 2008 Preparation of the paths and hardstanding in front to the stores is in progress. |
20th June 2008 The first load of concrete for the footings arrives at 9am. |
20th June 2008 The concrete is quickly discharged. Four more loads to go. |
|
|
|
|
|
|