3rd December 2008 The trees and undergrowth are being cleared from the east side of the site. Some of the larger trees will remain, and we are planting some smaller species around the perimeter of the site to replace the trees that have been removed. |
3rd December 2008 The car turning area is being prepared for tarmac. |
3rd December 2008 This is one of the low surface temperature radiators. |
3rd December 2008 Pipework for the heating is being run in the loft space. |
4th December 2008 Sanitaryware is being installed in the male toilet. |
4th December 2008 The car turning area is almost ready for tarmac. |
4th December 2008 The undergrowth has all been cleared. |
5th December 2008 Insulation is being placed in the loft space and further progress made with the heating pipework. |
5th December 2008 Tarmac is being spread and compacted over the car turning area, disabled parking bays and footpath. |
5th December 2008 This is the footpath, with its first layer of tarmac. |
6th December 2008 More painting is being completed this weekend - even the inside of the Hall cupboard. A big thank you for all the parents who have helped. |
6th December 2008 Extractor fans have been fitted in the toilets. |
6th December 2008 The heating is divided into two zones, one for the main Hall and the other for the Meeting Room. These are the two valves which control the zones. This will mean we only need to heat those areas of the building that are being used. |
6th December 2008 All the water pipework has been connected to the boiler. |
6th December 2008 This is the radiator in the kitchen. The kitchen itself should be fitted in the coming week. |
6th December 2008 The Meeting Room has been decorated. Two radiators are needed to heat this room. |
6th December 2008 This is the view from the front door. The rest of the tarmac should be completed in the coming week. |
6th December 2008 Clearance of the site continues. |
6th December 2008 The current appearance of the front. |
|
|