BOOKHAM SCOUTING CENTRE

Progress photographs - Week 25 (w/c 1st December 2008)


Home

News

Appeal

Existing HQ

The site

Plans

Images

Contact

Donate

Links

Progress photos

Sponsors

Project team



Select the week to view and click on the images to see a larger version...

StoresWeek 1Week 2Week 3Week 4Week 5
Week 6Week 7Week 8Week 9Week 10Week 11
Week 12Week 13Week 14Week 15Week 16Week 17
Week 18Week 19Week 20Week 21Week 22Week 23
Week 24Week 25Week 26Week 27Week 28Week 29
Week 30Week 31Week 32Week 33Week 34Week 35 plus



3rd December 2008
The trees and undergrowth are being cleared from the east side of the site. Some of the larger trees will remain, and we are planting some smaller species around the perimeter of the site to replace the trees that have been removed.

3rd December 2008
The car turning area is being prepared for tarmac.

3rd December 2008
This is one of the low surface temperature radiators.

3rd December 2008
Pipework for the heating is being run in the loft space.

4th December 2008
Sanitaryware is being installed in the male toilet.

4th December 2008
The car turning area is almost ready for tarmac.

4th December 2008
The undergrowth has all been cleared.

5th December 2008
Insulation is being placed in the loft space and further progress made with the heating pipework.

5th December 2008
Tarmac is being spread and compacted over the car turning area, disabled parking bays and footpath.

5th December 2008
This is the footpath, with its first layer of tarmac.

6th December 2008
More painting is being completed this weekend - even the inside of the Hall cupboard. A big thank you for all the parents who have helped.

6th December 2008
Extractor fans have been fitted in the toilets.

6th December 2008
The heating is divided into two zones, one for the main Hall and the other for the Meeting Room. These are the two valves which control the zones. This will mean we only need to heat those areas of the building that are being used.

6th December 2008
All the water pipework has been connected to the boiler.

6th December 2008
This is the radiator in the kitchen. The kitchen itself should be fitted in the coming week.

6th December 2008
The Meeting Room has been decorated. Two radiators are needed to heat this room.

6th December 2008
This is the view from the front door. The rest of the tarmac should be completed in the coming week.

6th December 2008
Clearance of the site continues.

6th December 2008
The current appearance of the front.

1st and 3rd Bookham Scout Groups - Registered Charity No 305772