 4th July 2008 The sub-base, damp-proof membrane, insulation, reinforcement and formwork for the main building slab have been installed, ready for the concrete to be poured |
 4th July 2008 Another view of the formwork and reinforcement. |
 4th July 2008 The concrete pump has arrived. |
 4th July 2008 This is the laser device which will be used to control the level of the slab. |
 4th July 2008 The first load of concrete arrives. Ten loads will be required. |
 4th July 2008 The concrete is delivered into the formwork by the pump. |
 4th July 2008 The slab has been filled to the required level and awaits final finishing. |
 4th July 2008 Once an initial set has occurred, power floating of the slab commences. This results in a very smooth, high tolerance finish. |
 5th July 2008 The finished slab, the following morning. A curing membrane has been applied to prevent the concrete from drying out too quickly. |
|
|
|
|
|
|