18th August 2008 Not much progress today - very wet. About one-third of the roof is on. |
19th August 2008 Nearly all of the roof panels have been installed. |
19th August 2008 Here is a view of the inside. Dry at last. |
20th August 2008 Leofric have started installing the gable end cladding. The panels are identical to those on the roof, except for the colour. |
20th August 2008 A close up of the gable end cladding. |
20th August 2008 This pile of windows is waiting to be installed. All the windows are uPVC, double glazed, with low emissivity toughened glass. This should limit the amount of heat loss through the windows and ensure we have no accidents with broken glass. |
20th August 2008 The very first window has been installed! |
20th August 2008 The gutter along the east side, facing away from the car park has been fixed. The gutters will drain into the large soakaways that have been constructed nearby (see Week 4). |
23rd August 2008 Internal view, looking towards the kitchen and toilets. |
23rd August 2008 Internal view, looking across the hall. |
23rd August 2008 All the south gable cladding and the windows in the east wall have been installed. |
|