BOOKHAM SCOUTING CENTRE

Progress photographs - Week 13 (w/c 8th September 2008)


Home

News

Appeal

Existing HQ

The site

Plans

Images

Contact

Donate

Links

Progress photos

Sponsors

Project team



Select the week to view and click on the images to see a larger version...

StoresWeek 1Week 2Week 3Week 4Week 5
Week 6Week 7Week 8Week 9Week 10Week 11
Week 12Week 13Week 14Week 15Week 16Week 17
Week 18Week 19Week 20Week 21Week 22Week 23
Week 24Week 25Week 26Week 27Week 28Week 29
Week 30Week 31Week 32Week 33Week 34Week 35 plus



8th September 2008
While Leofric continue work on the internal lining, Bisley have returned to complete some initial backfilling around the building.

8th September 2008
Backfilling on the car park side.

11th September 2008
The inside is being lined with OSB and plasterboard.

11th September 2008
These bricks are waiting to be used to form the front wall, either side of the entrance door.

12th September 2008
The first layer of the lining in the rear gable is finished. This will now be lined with a layer of plasterboard.

12th September 2008
The blockwork inner skin of the wall either side of the main entrance has been started.

12th September 2008
These walls form three sides of the disabed toilet.

12th September 2008
The is a view of the main entrance from inside.

12th September 2008
At the end of the day, the blockwork is shoulder high and the insulation is being installed.

1st and 3rd Bookham Scout Groups - Registered Charity No 305772