15th December 2008 The flooring has been delivered and is being conditioned to the temperature in the new building. |
15th December 2008 This is the sanitaryware for the disabled toilet. |
15th December 2008 The column casings have been painted. |
17th December 2008 The hot and cold water plumbing to the basins in the mens' toilet has been completed. |
17th December 2008 The disabled toilet sanitaryware is being fitted. |
17th December 2008 All the heating pipes have been insulated in the loft space. |
18th December 2008 The concrete floor in the building is still too damp to install the flooring, this de-humidifier should speed up the drying process. |
18th December 2008 The kitchen installation has started. The kitchen has been supplied by Howdens, at a heavily discounted price. |
18th December 2008 Another view of the kitchen. |
19th December 2008 This framework will be a cupboard in the corner of the ladies toilet to enclose the electrical consumer unit and other services. |
19th December 2008 The kitchen is proceeding rapidly. |
20th December 2008 A soffit has been fitted to the entrance recess. |
20th December 2008 The almost completed exterior. |
20th December 2008 Plumbing in the toilets is being boxed in. |
20th December 2008 More boxing in in progress. |
20th December 2008 At last - the entrance door has been delivered. |
|
|
|
|
|