12th November 2008 Timber cladding is now progressing on the car park side of the building. The gas meter box has been installed. |
12th November 2008 Plastering in the Main Hall is proceeding well |
12th November 2008 The electrical installation has started today. |
13th November 2008 The timber cladding on the front is almost complete |
13th November 2008 Plastering in progress in the Meeting Room. |
15th November 2008 Electrical cables are being installed in the loft space. |
15th November 2008 These are the internal doors. |
15th November 2008 The undercoat plaster in the meeting room has been finished. |
15th November 2008 Plastering has been finished on three walls of the main Hall. |
15th November 2008 Parents have been helping this weekend with the initial decoration of the toilets and kitchen. |
15th November 2008 Click on this photo to see a high resolution image. |
|