22nd June 2008 The concrete in the foundations has set. |
22nd June 2008 The car park area has been levelled and is being prepared for its sub-base. In the foreground the formwork for the edges of the concrete path in front of the stores is visible |
23rd June 2008 Another view of the car park. |
25th June 2008 Ducts being laid for gas and electricity services. |
26th June 2008 The foul sewer and telephone ducts have also been laid in the same trench. |
26th June 2008 Foul drains and service connections at the building. |
27th June 2008 Reinforcement steel for the main building slab. |
27th June 2008 This is the insulation that goes under the ground slab. The building has been designed to meet the stringent requirements of the recently updated Building Regulations, which aim to reduce the lifetime "carbon footprint" of buildings. |
|
|
|
|
|
|
|