6th October 2008 This opening will provide access to the space above the ceiling. |
6th October 2008 The posts supporting the end wall of the Hall are being encased in special plasterboard to provide additional fire resistance. |
6th October 2008 Hopefully this heap of plaster will be on the walls shortly. |
7th October 2008 Further progress is made on the brickwork around the entrance door. |
9th October 2008 The serving hatch between the Kitchen and the Hall has been formed. |
9th October 2008 Plasterboard is going up on the ceilings. This is the Meeting Room. |
9th October 2008 A view of the ceiling and "loft hatch" in the main corridor. |
12th October 2008 The entrance brickwork feature is finished. |
12th October 2008 The front of the building is now approaching its final appearance. Only the timber cladding remains to be fixed. |
12th October 2008 This pile of timber will form the cladding. It is Western Red Cedar, as commonly used in greenhouses. It is left untreated and is extremely resitant to fungal attack. Utimately it will weather to a grey colour. |
12th October 2008 The clading profle is a rebated feather edge. |
|