BOOKHAM SCOUTING CENTRE

Progress photographs - Week 23 (w/c 17th November 2008)


Home

News

Appeal

Existing HQ

The site

Plans

Images

Contact

Donate

Links

Progress photos

Sponsors

Project team



Select the week to view and click on the images to see a larger version...

StoresWeek 1Week 2Week 3Week 4Week 5
Week 6Week 7Week 8Week 9Week 10Week 11
Week 12Week 13Week 14Week 15Week 16Week 17
Week 18Week 19Week 20Week 21Week 22Week 23
Week 24Week 25Week 26Week 27Week 28Week 29
Week 30Week 31Week 32Week 33Week 34Week 35 plus



17th November 2008
Timber cladding to the car park side of the building continues.

17th November 2008
The groundworks contractor has returned to the site to finish the car park and paths.

17th November 2008
The Meeting Room has received its top coat of plaster.

17th November 2008
Thanks to the efforts of parents over the weekend, the store rooms (and the kitchen/toilets) have been painted.

17th November 2008
This is the kitchen, looking much brighter with its white paint.

18th November 2008
Excavation underway for the remainder of the car turning area and access footpath.

18th November 2008
The last part of the main Hall wall has received its first coat of plaster.

18th November 2008
Sanitaryware has been delivered.

18th November 2008
Cedar cladding continues around the car park side of the building.

20th November 2008
Light fittings in the Meeting Room.

20th November 2008
The internal doors are being primed before being hung.

20th November 2008
Cedar cladding is almost finished on this side of the building. Only one more wall to go!

21st November 2008
The internal doors in the Main Hall have been hung and architraves/skirtings fitted.

21st November 2008
Lights have been installed in the entrance corridor.

21st November 2008
The last of the cedar cladding has been started.

21st November 2008
The groundworks contractor is removing excess soil from the site.

22nd November 2008
Sub-base has been laid over the turning area and footpath.

22nd November 2008
This is the sub-base for the concrete footpath along the side of the building.

22nd November 2008
Tiling has started in the toilets. Like the painting, this is being done by volunteers.

1st and 3rd Bookham Scout Groups - Registered Charity No 305772