2nd September 2008 The verge flashing has been installed to seal the junction between the edge of the roof and the gable cladding. |
2nd September 2008 A ridge capping seals the top of the roof. |
2nd September 2008 Insulation of the walls has started. This is the first layer, which sits within the concrete panels. |
2nd September 2008 The second layer of insulation is placed over the first. The timber battens will support vertical timber studs to which the internal lining will be fixed. |
2nd September 2008 Another view of the second layer of insulation. |
4th September 2008 The last few windows have been installed. |
4th September 2008 Wall insulation continues. The joints between the boards are being taped. |
|
|
|
|
|