Progress photographs - Week 24 (w/c 24th November 2008)


Home

News

Appeal

Existing HQ

The site

Plans

Images

Contact

Donate

Links

Progress photos

Sponsors

Project team



Select the week to view and click on the images to see a larger version...

StoresWeek 1Week 2Week 3Week 4Week 5
Week 6Week 7Week 8Week 9Week 10Week 11
Week 12Week 13Week 14Week 15Week 16Week 17
Week 18Week 19Week 20Week 21Week 22Week 23
Week 24Week 25Week 26Week 27Week 28Week 29
Week 30Week 31Week 32Week 33Week 34Week 35 plus



25th November 2008
Sub-base, and formwork along the side of the building is ready for concreting to form a path.

25th November 2008
The concrete path will run right around the front of the building to the entrance. Work on the footpath from the gate has also started.

25th November 2008
.This precast concrete edging will form the edges of the footpath from the gate to the main entrance.

25th November 2008
The is the door from the Main Hall into the Meeting Room.

25th November 2008
Work has started on the heating system. The Main Hall will be heated by three fan convectors units fixed to the wall at high level.

25th November 2008
Tiling in the toilets continues. This is the Gents toilet. This work is being done by volunteers.

27th November 2008
The concrete path to the right of the main entrance and ...

27th November 2008
... around the far side of the building has been cast. It has been covered with hessian to protect it from frost. Progress can also be seen on the timber cladding which should be finished this week.

27th November 2008
Formwork has been installed for the concrete path around the car park side of the building.

27th November 2008
The heating boiler has been installed. This will provide hot water to radiators and also to the taps in the kitchen and toilets.

27th November 2008
Here are two of the wall mounted fan convectors in the Hall.

29th November 2008
Work continues on the entrance path.

29th November 2008
More decoration is being completed by parents this weekend. This is the corridor leading to the Meeting Room.

29th November 2008
The Meeting Room has been partially painted. The plaster is still too wet in places to complete the work.

29th November 2008
The Main Hall has received its first coat of paint.