25th November 2008 Sub-base, and formwork along the side of the building is ready for concreting to form a path. |
25th November 2008 The concrete path will run right around the front of the building to the entrance. Work on the footpath from the gate has also started. |
25th November 2008 .This precast concrete edging will form the edges of the footpath from the gate to the main entrance. |
25th November 2008 The is the door from the Main Hall into the Meeting Room. |
25th November 2008 Work has started on the heating system. The Main Hall will be heated by three fan convectors units fixed to the wall at high level. |
25th November 2008 Tiling in the toilets continues. This is the Gents toilet. This work is being done by volunteers. |
27th November 2008 The concrete path to the right of the main entrance and ... |
27th November 2008 ... around the far side of the building has been cast. It has been covered with hessian to protect it from frost. Progress can also be seen on the timber cladding which should be finished this week. |
27th November 2008 Formwork has been installed for the concrete path around the car park side of the building. |
27th November 2008 The heating boiler has been installed. This will provide hot water to radiators and also to the taps in the kitchen and toilets. |
27th November 2008 Here are two of the wall mounted fan convectors in the Hall. |
29th November 2008 Work continues on the entrance path. |
29th November 2008 More decoration is being completed by parents this weekend. This is the corridor leading to the Meeting Room. |
29th November 2008 The Meeting Room has been partially painted. The plaster is still too wet in places to complete the work. |
29th November 2008 The Main Hall has received its first coat of paint. |
| |
|
|
|
|