BOOKHAM SCOUTING CENTRE

Progress photographs - Week 26 (w/c 8th December 2008)


Home

News

Appeal

Existing HQ

The site

Plans

Images

Contact

Donate

Links

Progress photos

Sponsors

Project team



Select the week to view and click on the images to see a larger version...

StoresWeek 1Week 2Week 3Week 4Week 5
Week 6Week 7Week 8Week 9Week 10Week 11
Week 12Week 13Week 14Week 15Week 16Week 17
Week 18Week 19Week 20Week 21Week 22Week 23
Week 24Week 25Week 26Week 27Week 28Week 29
Week 30Week 31Week 32Week 33Week 34Week 35 plus



8th December 2008
Work is progressing on the car turning area.

8th December 2008
Limited funds mean we cannot afford to tarmac all of the parking area. Most of the surface will be finished with a crushed stone. This will also have environmental benefits as it means that it will limit the amount of rainfall being directed into the drains.

11th December 2008
The fire alarm system is being installed.

11th December 2008
The sanitaryware is being plumbed in.

11th December 2008
This is one of the low surface temperature radiators with its cover removed.

11th December 2008
More toilets being plumbed in.

11th December 2008
Most of the external works are now complete.

11th December 2008
The topsoil taken from the building and car park areas has been spread over the remainder of the site. This will need to be levelled and seeded once it has settled down.

13th December 2008
Difficult to show in a photo, but this boiler is now running and the building is warm!

13th December 2008
The columns in the side walls of the Main Hall and Meeting Room have been cased with MDF by one of the parents. Thank you Dougie.

13th December 2008
This weekend there have been more decorating sessions and this work is now essentially complete. A big thank you to all those who have helped.

13th December 2008
These are all the kitchen units, ready to be installed.

1st and 3rd Bookham Scout Groups - Registered Charity No 305772