8th December 2008 Work is progressing on the car turning area. |
8th December 2008 Limited funds mean we cannot afford to tarmac all of the parking area. Most of the surface will be finished with a crushed stone. This will also have environmental benefits as it means that it will limit the amount of rainfall being directed into the drains. |
11th December 2008 The fire alarm system is being installed. |
11th December 2008 The sanitaryware is being plumbed in. |
11th December 2008 This is one of the low surface temperature radiators with its cover removed. |
11th December 2008 More toilets being plumbed in. |
11th December 2008 Most of the external works are now complete. |
11th December 2008 The topsoil taken from the building and car park areas has been spread over the remainder of the site. This will need to be levelled and seeded once it has settled down. |
13th December 2008 Difficult to show in a photo, but this boiler is now running and the building is warm! |
13th December 2008 The columns in the side walls of the Main Hall and Meeting Room have been cased with MDF by one of the parents. Thank you Dougie. |
13th December 2008 This weekend there have been more decorating sessions and this work is now essentially complete. A big thank you to all those who have helped. |
13th December 2008 These are all the kitchen units, ready to be installed. |
|
|
|
|
|
|
|
|
|